Rate Plan is for customers who use power mainly for agricultural irrigation and drainage or threshing adjustment.
Agricultural lighting and Agriculture Power Plan are contract options that allow you to set a contract usage period, and no charges are incurred for periods outside of the contract usage period.
However, since maintenance and management of the electricity supply equipment are required even outside of the contracted usage period, we have set a minimum charge (minimum guaranteed charge) that will be collected on an annual basis (Note 1).
If you terminate the contract before the end of the contract period for the current year (Note 2), please be aware that you will be charged the "minimum guaranteed fee" up to the contract termination date.
- One year refers to the period from Meter reading date in January to the day before Meter reading date in January of the following year.
- Even if the contract is terminated midway through the contract period for the current year, we may still charge a "minimum guaranteed fee" up to the date of contract termination.
〔農事用電力A〕
Customers who use power for irrigation and drainage
〔農事用電力B〕
Customers who use power for threshing adjustment
(Fixed-rate supply) Customers with contracted power of 5kW or less
(Metered supply) Customers with contracted power exceeding 5kW and less than 50kW
〔農事用電灯〕新規受付を終了しております
Customers using agricultural moth traps
(circle)
|
Classification |
unit |
Unit price |
||
|
10月31日まで |
11月1日から |
|||
|
Base charge |
1kW |
682.29 |
824.73 |
|
|
Power usage charge |
Summer (July 1st to September 30th) |
1kWh |
12.78 |
12.76 |
|
Other seasons (October 1st to June 30th of the following year) |
1kWh |
11.70 |
11.68 |
|
- The unit price includes the equivalent of consumption tax, etc.
- If the power factor is greater than 85%, Base charge will be discounted by 5%, and if it is less than 85%, Base charge will be increased by 5%.
- If your usage is 0kWh, Base charge will be half the price.
|
Minimum guaranteed fee |
Contracted power × Base charge × 2 months ± Power factor surcharge (discount) |
(circle)
|
Classification |
unit |
Unit price |
|||
|
10月31日まで |
11月1日から |
||||
|
Fixed-price supply |
The first 30 days of each year |
0.5kW |
3,809.33 |
3,875.33 |
|
|
1kW |
5,429.99 |
5,561.99 |
|||
|
2kW |
8,670.68 |
8,934.68 |
|||
|
3kW |
11,911.67 |
12,307.67 |
|||
|
4kW |
15,152.66 |
15,680.66 |
|||
|
5kW |
18,393.35 |
19,053.35 |
|||
|
For each day exceeding 30 days |
0.5kW |
30.91 |
33.11 |
||
|
1kW |
61.83 |
66.23 |
|||
|
2kW |
123.66 |
132.46 |
|||
|
3kW |
185.49 |
198.69 |
|||
|
4kW |
247.32 |
264.92 |
|||
|
5kW |
309.15 |
331.15 |
|||
|
Pay-per-use supply |
Base charge |
1kW |
10% increase in applicable Low- Voltage Power charges |
10% increase in applicable Low- Voltage Power charges |
|
|
Power usage charge |
summer |
1kWh |
19.09 |
19.07 |
|
|
Other seasons |
1kWh |
17.25 |
17.23 |
||
- The unit price includes the equivalent of consumption tax, etc.
- "Summer" refers to the period from July 1 to September 30. "Other seasons" refers to periods other than "summer."
|
Minimum guaranteed fee |
Fixed price supply (Note) |
Charges for the first 30 days per contracted power capacity |
|
Pay-per-use supply |
Contracted power × 10% increase on Base charge for Low- Voltage Power × 2 months ± power factor surcharge (discount) |
- In addition to the above, we will also charge Adjustments for fuel costs, etc., an adjustment for universal services on remote islands, and Renewable Energy Generation Promotion Surcharge.
(circle)
|
Classification |
unit |
Unit price |
||
|
10月31日まで |
11月1日から |
|||
|
Customer charges |
1contract |
55.00 |
55.00 |
|
|
Electricity charges |
Up to 10W |
1 lamp |
97.73 |
104.25 |
|
Up to 20W |
1 lamp |
150.40 |
163.43 |
|
|
Up to 40W |
1 lamp |
257.88 |
283.93 |
|
|
Up to 60W |
1 lamp |
364.25 |
403.34 |
|
|
Up to 100W |
1 lamp |
578.14 |
643.27 |
|
|
For every 100W over 100W |
1 lamp |
578.14 |
643.27 |
|
|
Small equipment fee |
Devices up to 50VA |
1 device |
257.95 |
277.40 |
|
Devices up to 100VA |
1 device |
393.77 |
432.68 |
|
|
For every 50VA over 100VA |
1 device |
197.45 |
216.90 |
|
- The unit price includes the equivalent of consumption tax, etc.
|
Minimum guaranteed fee |
Customer rates + Lighting and small appliance charges |
- In addition to the above, we will also charge Adjustments for fuel costs, etc., an adjustment for universal services on remote islands, and Renewable Energy Generation Promotion Surcharge.