If you have installed or modified renewable energy Power generation equipment and wish to purchase the renewable energy electricity generated by that equipment, you will need to apply to our company. The main steps required to start purchasing are as follows:
1. Application for Benefit Contract
申込代行者さま{icon"icon_arr04_right.svg"}九州電力
{icon"icon_arr04_down.svg"}
<Procedures for application agents and customers>
Business plan approval procedure
申込代行者さま・お客さま{icon"icon_arr04_lr.svg"}国
{icon"icon_arr04_down.svg"}
2.Technology Review
Kyushu Electric Power Transmission and Distribution
{icon"icon_arr04_down.svg"}
3. Information on grid interconnection contracts
九州電力送配電{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}申込代行者さま{icon"icon_arr04_right.svg"}お客さま
It will take approximately one month from the time you apply for the benefit contract until this notification is sent.
{icon"icon_arr04_down.svg"}
4. Installation of measuring instruments, etc.
Kyushu Electric Power Transmission and Distribution
{icon"icon_arr04_down.svg"}
5. Information on Electricity Supply Contract
九州電力{icon"icon_arr04_right.svg"}申込代行者さま(お客さま)
{icon"icon_arr04_down.svg"}
6. Start receiving benefits
九州電力{icon"icon_arr04_right.svg"}お客さま
{icon"icon_arr04_down.svg"}
7. Notification of power generation amount and payment
九州電力{icon"icon_arr04_right.svg"}お客さま
- Each month, Kyushu Electric Power Transmission and Distribution will read Kyushu Electric Power Transmission and Distribution meter on Meter reading date set by the company, and will notify you of the amount of electricity we will purchase, the price, etc. on a "Purchased power amount Confirmation Sheet."
- The fee will be transferred to the account you specify in advance.
If you have installed or modified renewable energy Power generation equipment and wish to purchase the renewable energy electricity generated by that equipment, you will need to apply to our company. The main steps required to start purchasing are as follows:
1. Advance consultation (optional)
申込代行者さま・お客さま{icon"icon_arr04_right.svg"}九州電力送配電
2. Connection Consideration Application
申込代行者さま{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}九州電力送配電
It takes about one month from pre-consultation to application.
{icon"icon_arr04_down.svg"}
3. Answer to the connection consideration results
九州電力送配電{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}申込代行者さま
We will respond within 2 to 3 months from the date of your connection application.
{icon"icon_arr04_down.svg"}
4. Connection contract application
申込代行者さま{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}九州電力送配電
{icon"icon_arr04_down.svg"}
<Procedures for application agents and customers>
Business plan approval procedure
申込代行者さま・お客さま{icon"icon_arr04_lr.svg"}国
{icon"icon_arr04_down.svg"}
5.Consent to interconnection, invoicing and payment of construction cost contributions
九州電力送配電{icon"icon_arr04_right.svg"}九州電力{icon"icon_arr04_right.svg"}申込代行者さま
{icon"icon_arr04_down.svg"}
6.Detailed Design
Kyushu Electric Power Transmission and Distribution
{icon"icon_arr04_down.svg"}
7. Contract Procedures
お客さま{icon"icon_arr04_right.svg"}九州電力
{icon"icon_arr04_down.svg"}
8. Start of Benefit Receipt
お客さま{icon"icon_arr04_lr.svg"}九州電力
{icon"icon_arr04_down.svg"}
9. Notification of power generation amount and payment
お客さま{icon"icon_arr04_lr.svg"}九州電力
The terms of the contract for grid connection and electricity receipt when a power generation company supplies electricity generated by renewable energy Power generation equipment to our company and our company receives that electricity.
Please use this form when applying for FIT-certified renewable Power generation equipment with an output of less than 50kW.
Please use this form when applying for FIT-certified renewable Power generation equipment with an output of 50 kW or more.
Please use this form when applying for non-FIT facilities (not scheduled to obtain FIT certification) with renewable energy Power generation equipment output of less than 50kW.
Please use this form when applying for non-FIT facilities (not scheduled to obtain FIT certification) with renewable energy Power generation equipment output of 50 kW or more.
Please use this form if you are installing renewable energy Power generation equipment and a storage battery together.
Please use this form when applying for grid connection for Power generation equipment with a reverse power flow of less than 50kW to our company.